Eni: Armada Olombendo FPSO vessel ready to sail to Block 15/06, offshore Angola

Singapore, 14 October 2016 - Eni announces that the naming ceremony of the “Armada Olombendo” floating production, storage and offloading (FPSO) vessel was held today in Singapore. The FPSO shall operate in Block 15/06, offshore Angola, for the East Hub Development Project. The vessel will soon be ready to sail to its final destination where, once in position, will commence mooring and hook-up operations.

Today, Eni and its partners reached a key milestone towards achieving the first oil from East Hub Development Project, which is planned by the first half of 2017. This follows the successful stream of start-ups in the West Hub Project, in the same Block 15/06, which is the only Block of those awarded in the 2006 bid round that has achieved production.

The East Hub Development Project encompasses 9 subsea wells, of which 5 are producers and 4 are water injectors, in water depth ranging between 450 and 550 metres. The hydrocarbons which are produced from these wells will be transported via a pipeline system to the FPSO to be treated and stored prior to export.

Eni is the Operator of Block 15/06 with a 36.84% stake. The other partners in the joint venture are Sonangol Pesquisa e Produção (36.84%) and SSI Fifteen Limited (26.32%).

Eni has been present in Angola since 1980 with net current production of 135,000 barrels of oil equivalent per day.
escveritas
Site Admin
Posts: 3181
Joined: Sat Aug 29, 2020 5:40 am
Location: Singapore
Contact:
Singapore

Re: [Angola] Armada Olombendo

Unread post by escveritas »

Eni Achieves First Oil at Cabaça North off Angola

Eni has started production from the Cabaça North development project in Block 15/06 of the Angolan deep offshore, via the Armada Olombendo FPSO vessel. The development, with an expected peak production rate in the range of 15,000 B/D, will increase and sustain the plateau of the FPSO with an overall capacity of 100,000 B/D.

This is the second startup achieved by Eni Angola in 2021, after the Cuica early production achieved in July. A third startup is expected within the next few months, with the Ndungu early production in the western area of Block 15/06.

Block 15/06 is operated by Eni Angola with a 36.84% share. Sonangol Pesquisa e Produção (36.84%) and SSI Fifteen Limited (26.32%) are joint venture partners. Further to Block 15/06, Eni is the operator of exploration blocks Cabinda North, Cabinda Centro, 1/14, and 28, as well as of the New Gas Consortium (NGC).

In addition, Eni has stakes in the nonoperated blocks 0 (Cabinda), 3/05, 3/05A, 14, 14 K/A-IMI, and 15, and in the Angola LNG project.