[Australia] Stag

Post Reply
escveritas
Site Admin
Posts: 3186
Joined: Sat Aug 29, 2020 5:40 am
Location: Singapore
Contact:
Singapore

[Australia] Stag

Unread post by escveritas »

The Stag oilfield was acquired by Jadestone through its wholly-owned subsidiary Jadestone Australia on November 11, 2016.

The field was developed using a fixed leg, 12 slot manned central processing facility platform with a liquids production capacity of 50,000 bbl/d, of which 30,000 bbl/d is for oil. This is connected, by an eight inch underwater export pipeline, to a pipeline end manifold and Floating Storage and Offloading vessel (“FSO”), via a catenary anchor leg mooring buoy. Shuttle tankers transfer the oil from the FSO to shore.

As at December 31, 2017, Stag had 2P reserves of 17.1 MMbbls (gross and net) with a value of US$84.2 million (NPV10). The field has 3P reserves of 22.7 MMbbls and 2C oil resources of 2.7 MMbbls (gross and net).

The field produces a biodegraded oil with a gravity of 19 API. Oil production peaked at approximately 26,000 stb/d in 2000 but has now fallen to approximately 3,600 stb/d via 11 production wells. Field water production is approximately 22,000 bbl/d and the watercut is approximately 88 per cent.

The Company has planned an infill drilling campaign to drill one new well in 2018, two in 2019 and two in 2020 with an estimated total associated cost of US$112 million.
escveritas
Site Admin
Posts: 3186
Joined: Sat Aug 29, 2020 5:40 am
Location: Singapore
Contact:
Singapore

Re: [Australia] Stag

Unread post by escveritas »

New Stag Offtake Arrangements

September 3, 2020—Singapore: Jadestone Energy Inc. (AIM:JSE) (“Jadestone”, or the “Company”), an independent oil and gas production company focused on the Asia Pacific region, announces new offtake arrangements for its Stag oilfield.

Jadestone’s 100% owned and operated Stag oilfield produces crude oil via a fixed leg, central processing facility platform, which, since the field’s original development, has been offloaded to a floating storage and offloading vessel (“FSO”), the Dampier Spirit, which is moored to a catenary anchor leg mooring buoy. In May 2020, the owner of the Dampier Spirit advised the Company of its intention to retire the Dampier Spirit later in 2020, and, as required under the terms of their agreement with Jadestone, they have been unable to provide a suitable replacement vessel.

As a consequence, the Company has developed a new operating strategy, utilising offtake tankers to directly offload Stag crude oil, in place of the existing long term leased FSO. To implement this strategy Jadestone has awarded a contract to a respected international tanker provider who will supply modern double hulled tankers, operated to the highest safety and environmental standards. This new operating model has significant environmental risk mitigants over the existing model, by eliminating the need for ship to ship oil transfers in field. These arrangements are expected to realise annual savings of approximately 20% over the current FSO operation.

The first offtake tanker is scheduled to arrive in the field coincident with the Dampier Spirit departure in mid September 2020. Ultimately multiple offtake tankers will rotate through the field on a schedule that optimises production continuity.

The new model has also required a change to the regulatory structure that was in place for the FSO. Jadestone has worked with Australian regulators, the National Offshore Petroleum Safety and Environmental Management Authority and the Australian Maritime Safety Authority (“AMSA”), to ensure the model complies with all relevant laws and regulations and to obtain their acceptance. This includes both the requisite updates to the Company’s safety case for the Stag asset, and agreement that the vessels should be regulated by AMSA.