[Australia] Bayu-Undan and Darwin LNG

Post Reply
escveritas
Site Admin
Posts: 3181
Joined: Sat Aug 29, 2020 5:40 am
Location: Singapore
Contact:
Singapore

[Australia] Bayu-Undan and Darwin LNG

Unread post by escveritas »

Image

INPEX has an 11.37812 per cent interest in the Bayu-Undan offshore gas and condensate field in the Timor Sea and a corresponding interest in the Darwin LNG facility (DLNG) at Wickham Point near Darwin.

Bayu-Undan, operated by ConocoPhillips, has been a major contributor to the Timor-Leste economy for 16 years. The field is 250 kilometres southeast of Suai in Timor-Leste and 500 kilometres northwest of the Northern Territory in Australia.

Gas travels through a 502 kilometre pipeline from the Bayu-Undan Field to Darwin in the Northern Territory where it is converted to LNG and shipped to international markets.

A successful project for all stakeholders, the field is entering the final phase of its lifecycle. The operation will be decommissioned once the end of its economic production is reached sometime between 2021 to 2023.

DLNG is currently considering options for backfilling the facility beyond the depletion of Bayu-Undan.

Santos recently announced their intention to acquire the interests and Operatorship of Bayu-Undan and DLNG from ConocoPhillips.
escveritas
Site Admin
Posts: 3181
Joined: Sat Aug 29, 2020 5:40 am
Location: Singapore
Contact:
Singapore

Re: [Australia] Bayu-Undan and Darwin LNG

Unread post by escveritas »

BAYU-UNDAN PHASE 3C INFILL PRODUCTION EXCEEDS EXPECTATIONS

Santos, as operator of the Bayu-Undan Joint Venture, today announced that production from the Phase 3C infill drilling program at the Bayu-Undan field had begun with the first well producing a better than anticipated outcome.

The first well has been brought online at 178 million standard cubic feet per day (mmscfd) of gas and 11,350 barrels per day (bbl/d) of liquids, significantly increasing liquids production to over 25,000 bbl/d from the field and increasing offshore well capacity for supply of gas to the Darwin LNG plant.

The Noble Tom Prosser jack-up rig has now commenced drilling the second of the three wells, with the program expected to be completed early next year and will maximise value from the Bayu-Undan field.

Santos Managing Director and Chief Executive Officer Kevin Gallagher said: “We are delighted to see first production from the 3C program, which is immediately delivering value to both the Bayu-Undan Joint Venture and the people of Timor-Leste and importantly helps extend the life of Bayu-Undan and the jobs and investment that rely on it.

“Following the successful result from the first of the Van Gogh Phase 2 infill wells, today’s results are another example of Santos creating incremental value from acquired assets.

“We’ve seen a better than expected reservoir outcome with this first well of the campaign, with successful results across both the primary and secondary targets in the well and a much higher initial gas production rate than expected.”

“It has not come without its challenges, managing crew movements with COVID-19 outbreaks either side of the Timor Sea, so I want to acknowledge the efforts of our team, our Joint Venture partners and specifically the Timor-Leste regulator, Autoridade Nacional do Petróleo e Minerais (ANPM), in keeping this exciting program on track.”

The successful drilling and tie-in of the first of three new wells comes six months after a Final Investment Decision and has lifted natural gas and liquids production for the field in Timor-Leste offshore waters.

ANPM President Florentino Soares Ferreira said: “From the outset, the Phase 3C program has been seen as an opportunity to maximise the ultimate recovery in the Bayu-Undan field. This was of course a calculated decision from the regulatory side considering we are working under the Production Sharing Agreement regime in which the cost recovery scheme is a fundamental element in our assessment.

“Managing the mobilisation of the crews between Bayu-Undan and hotspot areas during the pandemic has been a challenging task, but with great synergy between the Operator and ANPM, the Phase 3C operation has been smooth.

“The successful result of the first 3C well has proven to us that our decision for approval was correct. We can now give additional hope to Timor-Leste with the increase of production and extension of the Bayu-Undan field life, and we look forward to the success of the two remaining 3C wells.”

Santos has a 43.4% operated interest in Bayu-Undan. The remaining interest is held by SK E&S (25%), INPEX (11.4%), Eni (11%), JERA (6.1%), and Tokyo Gas (3.1%).
escveritas
Site Admin
Posts: 3181
Joined: Sat Aug 29, 2020 5:40 am
Location: Singapore
Contact:
Singapore

Re: [Australia] Bayu-Undan and Darwin LNG

Unread post by escveritas »

McDermott Completes Subsea Campaign for Bayu-Undan Gas Field

Bayu-Undan Infill Well Phase 3C Project Delivered Safely and on Time



HOUSTON, March 10, 2022 /PRNewswire/ -- McDermott International recently completed work under its first subsea, engineering, procurement, construction and installation (EPCI) contract with Santos NA (19-12) Pty Ltd for the Bayu-Undan Infill Well Phase 3C Project in the Timor Sea located approximately 310 miles (500 kilometers) off the northwest coast of Darwin, Australia, and 124 miles (200 kilometers) off the southeast coast of Timor-Leste.

The Bayu-Undan field is one of Timor-Leste's largest gas fields. Work on the Phase 3C Project commenced in May and concluded in December 2021. McDermott's scope involved a tieback of a single in-field well to existing facilities, re-using existing flexible flowline, with a new umbilical and certain infrastructure.

"McDermott completed the scope within nine months of award," said Mahesh Swaminathan, McDermott's Senior Vice President, Asia Pacific, Subsea & Deepwater. "McDermott's industry-leading health, safety and environmental protocols were effective in mitigating certain risks associated with executing a subsea EPCI scope during the COVID-19 pandemic."

The project is another example of McDermott's growing success in the subsea and deepwater business. A key to the execution was recovery of existing flexible flowlines, flushing to clear hydrocarbons, re-laying and a tieback from a new in-field well to the existing Bayu-Undan facility.

Recovery and reusing existing flexible flowlines was a significant factor in enabling the work to be completed nine months from award and within the project schedule.

In line with McDermott and Santos' sustainability goals, local Timor-Leste businesses were engaged to execute components of the project, including concrete mattress manufacture, marine training and experience onboard the primary installation vessel—the Lay Vessel 108.