[Senegal] Sangomar

Post Reply
escveritas
Site Admin
Posts: 575
Joined: Sat Aug 29, 2020 5:40 am

[Senegal] Sangomar

Unread post by escveritas »

Image

The Sangomar Field Development is poised to be Senegal's first offshore oil development.
The Sangomar field (formerly the SNE field), containing both oil and gas, is located 100 kilometres south of Dakar. Work on the Sangomar Field Development commenced in early 2020 and first oil production is targeted in 2023.

The initial phase is referred to as the Sangomar Field Development Phase 1 (the Sangomar Field Development). This phase will focus on developing the less complex reservoir units and testing other reservoirs to support gas export to shore. This phase of the development will target approximately 230 million barrels of crude oil.

Woodside has taken early action to proactively manage the emerging impacts of COVID-19 on the supply chain and project schedule and is working with project contractors, the Government of the Republic of Senegal and our joint venture partners to evaluate options to reduce total cost and near-term spend whilst protecting the overall value of the investment.

The Rufisque Offshore, Sangomar Offshore and Sangomar Deep Offshore joint venture, comprising Woodside (Operator), Capricorn Senegal Limited (a subsidiary of Cairn Energy PLC) FAR Limited and Societé des Petroles du Sénégal (Petrosen), is committed to the development of Sangomar field in accordance with international industry best practice and relevant government regulations.

Key stats 2023 targeting first production
100,000 bbl/day estimated production capacity
60 + communities engaged
escveritas
Site Admin
Posts: 575
Joined: Sat Aug 29, 2020 5:40 am

Re: [Senegal] Sangomar

Unread post by escveritas »

SANGOMAR FIELD DEVELOPMENT EXPLOITATION AUTHORISATION

The Government of Senegal has approved the Rufisque Offshore, Sangomar Offshore and Sangomar Deep Offshore (RSSD) joint venture Exploitation Plan and granted the Exploitation Authorisation for the Sangomar Field Development.

Commencement of the execute phase of the Sangomar Field Development Phase 1 (Sangomar Development) is subject to final execution of the Host Government Agreement with the Government of Senegal and the approval and award of key contracts.

The Sangomar Development concept is a stand-alone floating production storage and offloading (FPSO) facility with 23 subsea wells and supporting subsea infrastructure. The FPSO, expected to have a production capacity of 100,000 bbl/day, will process the oil before it is exported to market via tankers. First oil is targeted in early 2023.

The FPSO will allow for the integration of potential future development phases, including gas export to shore and future subsea tie-backs.

The RSSD joint venture comprises Woodside Energy (Senegal) B.V., Capricorn Senegal Limited (a subsidiary of Cairn Energy PLC), FAR Ltd and Petrosen (the Senegal National Oil Company).
escveritas
Site Admin
Posts: 575
Joined: Sat Aug 29, 2020 5:40 am

Re: [Senegal] Sangomar

Unread post by escveritas »

SANGOMAR TRANSACTION UPDATE
4 September 2020

Woodside Energy (Senegal) B.V. has entered into a binding sale and purchase agreement to acquire Capricorn Senegal Limited’s entire participating interest in the Rufisque Offshore, Sangomar Offshore and Sangomar Deep Offshore (RSSD) joint venture. This follows Woodside’s exercise of its pre-emptive rights announced on 17 August 2020.

Completion of the acquisition is subject to Government of Senegal approval, Cairn Energy PLC shareholder approval and other customary conditions precedent, and is targeted for Q4 2020. Following completion, Woodside’s equity interest will increase to approximately 68.33% in the Sangomar exploitation area and to 75% for the remaining RSSD evaluation area. Woodside will remain operator.
escveritas
Site Admin
Posts: 575
Joined: Sat Aug 29, 2020 5:40 am

Re: [Senegal] Sangomar

Unread post by escveritas »

SOFEC awarded External Turret Mooring System for Sangomar Field

SOFEC, Inc. (“SOFEC”) announced today that it has been awarded an external turret supply contract by MODEC for a Floating Production Storage and Offloading (FPSO) vessel for the Sangomar (formerly SNE) Field Development Phase 1 (Sangomar Field Development) project in the Sangomar Offshore and Sangomar Offshore Deep oil blocks, located offshore Senegal. MODEC will supply the FPSO under an FPSO Purchase Contract to Woodside1. The FPSO will be deployed in the Sangomar field located approximately 100 kilometers south of Dakar, Senegal. The Sangomar Field Development is expected to be Senegal’s first offshore oil development. The FPSO is scheduled for delivery to support the production of first oil in early 2023 and will be moored in approximately 780 meters water depth.
escveritas
Site Admin
Posts: 575
Joined: Sat Aug 29, 2020 5:40 am

Re: [Senegal] Sangomar

Unread post by escveritas »

FPSO Sangomar External Turret

Scope of Work

SOFEC will design, construct, and fabricate an external turret for the Sangomar (formerly SNE) Field Development Phase 1 project located in the Sangomar Offshore and Sangomar Offshore Deep oil blocks, located offshore Senegal.

The FPSO will be deployed at the Sangomar field located approximately 100 kilometers south of Dakar, Senegal. The Sangomar Field Development is expected to be Senegal’s first offshore oil development. Scheduled for delivery in early 2023, the FPSO vessel will be permanently moored at a water depth of approximately 780 meters.

The FPSO will be capable of processing 100,000 barrels of crude oil per day, 130 million standard cubic feet of gas per day, 145,000 barrels of water injection per day and will have minimum storage capacity of 1,300,000 barrels of crude oil.

The SOFEC external turret mooring system will be ABS classed.

General Description

Client Name: Woodside Energy
Contract Award: December 2019
Installation Date: Planned for 2023
First Oil: Planned for 2023
Vessel Size: 282,000 dwt
Storage Capacity: 1,300,000 bbls
Water Depth: 780 m (2,558ft)
Fabrication: Turret - TBD
Topsides - TBD
Vessel - TBD

Design Environmental Criteria

100-year storm
Sig. Wave Height: 6.9 m (22.6 ft)
Wind Velocity: 19.5 m/s (38 kts)
Current: 1.16 m/s (2.3 kts)

Fluid Swivel Assembly

TBD

Riser System

Fifteen risers and umbilicals