Operating in more than 7,000 feet of water and located approximately 150 miles south of New Orleans, Atlantis’ production capacity is approximately 200,000 barrels of oil and 180 million cubic feet of gas per day.

The Atlantis North project includes the drilling and completion new wells and the addition of subsea infrastructure to tieback to bp’s existing Atlantis platform. It will utilize available production capacity at the Atlantis hub.

Image
escveritas
Site Admin
Posts: 3181
Joined: Sat Aug 29, 2020 5:40 am
Location: Singapore
Contact:
Singapore

Re: [US GOM] Atlantis

Unread post by escveritas »

Atlantis Phase 3 starts up, delivering resilient and focused hydrocarbons

Atlantis Phase 3, bp’s first major project start-up of 2020, was completed safely and on time despite the unprecedented challenges of a global pandemic. The project represents a key component in the transformation of bp into an integrated energy company.

Image

Image

Image

Image

The Atlantis platform is located in the Gulf of Mexico, an area that will play an integral role in delivering hydrocarbons safely, efficiently and with a lower carbon footprint.

Phase 3 includes the construction of a new subsea production system for eight new wells tied into Atlantis. The development sits 150 miles south of New Orleans and 7,000 feet below the surface. The new wells are expected to boost production at the platform by an estimated 36,000 barrels of oil equivalent a day gross at its peak.

Resilient and focused hydrocarbons

“With this project, we were able to develop additional resources close to the current Atlantis platform, which allowed us to use existing infrastructure to access and deliver these barrels at low cost and in rapid time,” said Starlee Sykes, senior vice president, Gulf of Mexico and Canada.

“This is a great example of how oil and gas projects support bp's strategy by focusing our efforts in the basins we know best and close to existing infrastructure,” she said.

Digital technology and innovation

Ewan Drummond, senior vice president of production & operations – projects, also highlighted the innovative techniques that helped get the project to startup.

“It demonstrates one of our distinct sources of differentiation – driving digital and innovation – thanks to our use of advanced seismic imaging to identify the ‘field within a field’ and then design this new subsea system,” he said.