[Norway] Wisting FPSO

Post Reply
escveritas
Site Admin
Posts: 3181
Joined: Sat Aug 29, 2020 5:40 am
Location: Singapore
Contact:
Singapore

[Norway] Wisting FPSO

Unread post by escveritas »

Equinor awards Wisting FPSO Study Contract to Sevan SSP

Image

Sevan SSP is pleased to announce that Equinor, together with the Wisting Licence partners, has awarded Sevan SSP a Study Contract for the Wisting FPSO, based on Sevan’s cylindrical hull design.

The Sevan design has been subject to various assessments from the Wisting license in recent years and participating in the concept selection studies is considered a significant achievement for the Sevan technology. Sevan SSP is now eager to start this next phase of work.
escveritas
Site Admin
Posts: 3181
Joined: Sat Aug 29, 2020 5:40 am
Location: Singapore
Contact:
Singapore

Re: Wisting FPSO

Unread post by escveritas »

Equinor has, on behalf of the Wisting licence partners, awarded contracts for concept studies to further progress of the project development towards a final concept select decision.

“Wisting is a considerable oil field in the Barents Sea, and we are cooperating well with our partners in further maturing the project. Founded on experience and synergy potential within the project-portfolio we have assessed different development alternatives to identify potential solutions for a cost-effective and optimal field development” says Trond Bokn, acting senior vice president for project development in Equinor.

“Based on this work, the licence partners have decided to further assess a floating production unit based on a circular FPSO solution (floating production, storage and offloading). However, a lot of work remains before we can make a final concept select during second quarter of 2021,” says Bokn.

Equinor and the industry have ambitious plans for reducing greenhouse gas emissions from activities on the Norwegian continental shelf. The Wisting partners are focused on reducing the carbon footprint of the production to the lowest extent feasible.

“Electrification is considered a possible option for reducing field emissions. The project will study a power-from-shore solution for a circular FPSO going forward,” says Bokn.

In 2019, the authorities approved a transfer of the Wisting operatorship to Equinor in the development phase, while OMV will resume operatorship in the production phase. Equinor is leading the development project and personnel from OMV is well integrated in the project organisation.

Suppliers who have been awarded contracts in connection with the start of Wisting concept studies:
  • FPSO: Aker Solutions, KBR Ltd., Sevan SSP and Aibel
  • SURF (Subsea Production and Processing Equipment, Umbilical, Risers and Flowlines): Aker Solutions, TechnipFMC, OneSubsea Processing, IKM Ocean Design and Kongsberg Maritime
An investment decision for Wisting is planned at the end of 2022.

Partners: Equinor (35%), OMV (Norge) AS (25%), Petoro AS (20%) and Idemitsu Petroleum Norge AS (20%).
Post Reply

Return to “Sembcorp Marine”

Who is online

Users browsing this forum: No registered users and 3 guests